Cognitio College (Kowloon), Kai Tak, Hong Kong

Cognitio College (Kowloon), Kai Tak, Hong Kong


 

 

A new 30-classroom secondary school is being delivered under NEC contracts in Hong Kong’s Kai Tak development zone in Kowloon.

In a double first for the government’s Architectural Services Department (ArchSD), quantity surveying services for Cognitio College (Kowloon)’s new HK$447 million (£45 million) campus have been procured with an NEC3 Professional Services Contract and construction works have been let using an NEC Engineering and Construction Contract (ECC) Option B (priced contract with bill of quantities).

ArchSD engaged construction consultant Northcroft Hong Kong Limited to provide quantity surveying services under a HK$2.5 million (£250,000) PSC in July 2016. In addition, having successfully used ECC Option A (priced contract with activity schedule) for construction of the HK$3 billion (£300 million) Tin Shui Wai Hospital project, ArchSD is now trialling ECC Option B for the school’s main works contract. Contractor Hanison Construction Company Limited started on site in March 2017 and is due to complete the five-storey, 13 500m2 building by early 2019.

As well as 30 classrooms, the new school provides other teaching rooms and facilities, an assembly hall, a covered playground, two basketball courts, a running track and numerous other state-of-the-art student and staff facilities. Cognitio College (Kowloon) is moving to the new building from its existing premises in Wong Tai Sin district in time for the 2019/2020 academic year.

P&T Architects & Engineers Ltd. is the lead consultant, providing architectural, structural and building services consultancy services, and Urbis Ltd. is the landscape sub-consultant. ArchSD also engaged Mott MacDonald as NEC advisor to support NEC implementation on the project.

Enhancing Project Performance

According to ArchSD’s project manager Willy Yeung, ‘The NEC provides a “contractual partnering” approach by requiring contracting parties to work together “in a spirit of mutual trust and co-operation”. We believe this helps to enhance project performance.’ 

He says the project team held a series of NEC and partnering training sessions at the start of the project. ‘This helped the parties become more effective and efficient in their use of NEC processes, such as early warnings, risk reduction meetings, accepted programmes and compensation events.

‘For example, though effective use of early warnings and risk-reduction meetings, the project team and contractor were able to deploy their expertise through contractual partnering to resolve the problem of unforeseen ground conditions and minimise the cost and time implications. NEC’s requirement for enhanced communications within contractual timeframes has also helped to expedite resolution of all subsequent contract issues.’

Yeung concludes, ‘Overall, collaborative risk management by means of NEC early warnings and risk reduction meetings has helped us to achieve proactive identification and mitigation of project risks. This has enabled us to remain on target to achieve successful handover of a much-needed school for commissioning in the 2019/2020 academic year.’.

Benefits of NEC

  • NEC contracts enhance project performance though a ‘contractual partnering’ approach, with the parties obliged to work ‘in a spirit of mutual trust and co-operation’.
  • Collaborative risk management by means of NEC early warnings and risk reduction meetings helps to achieve proactive identification and mitigation of project risks.
  • NEC requirement for enhanced communications within contractual timeframes helps to expedite resolution of contract issues.
Recent Projects

Recent projects

Gatwick Airport Station development, UK

Gatwick Airport Station development, UK

NEC Users’ Group platinum member Network Rail has used NEC contracts to deliver a complex £249 million upgrade of Gatwick Airport Station in southern England.

Read more
Babbage Building, University of Plymouth, UK

Babbage Building, University of Plymouth, UK

NEC has been used to refurbish and extend a major university engineering and design facility in south- west England.

Read more
Mill Fleam flood pumping station, Derby, UK

Mill Fleam flood pumping station, Derby, UK

Derby City Council has used NEC to deliver an award-winning scheme to protect around 250 city-centre commercial properties from the increasing risk of flooding.

Read more
View all projects