Crossrail is one of the largest infrastructure projects of its kind currently being undertaken in Europe. It is building 42km of tunnels, 9 new stations and improving 30 more. The finished railway, which will be named the Elizabeth line, will be a fully accessible route of 40 stations from Reading and Heathrow in the west to Shenfield and Abbey Wood in the east.
The Crossrail project is expected to open the central section of the Elizabeth line near the end of 2021 with up to 12 trains per hour during peak.
The central section through London includes 42km of new rail tunnels, eight new sub-surface stations, shafts for ventilation and escape, provision of all necessary railway systems and a mainline train fleet allowing services along its overall 118km route. NEC3 contracts have been used to procure all central section works and systems requirements.
Achieving Excellence
Steve Rowsell, Interim Head of Procurement between 2008 and 2010, said "Crossrail's approach to procurement is aligned with the UK government's achieving excellence in construction principles, including a fair allocation of risk and reward, early involvement of the supply chain, minimising of interface risks, incentivising performance and selection of suppliers on the basis of best value.
"Following a review of available contracts and lessons learnt from recent major projects, we decided to use the NEC3 suite because it supports the desired culture and way of working, provides robust contract management processes, achieves a fair and sensible allocation of risk and can be used for all project requirements to give consistency in approach.
"Crossrail is a wholly owned subsidiary of Transport for London (TfL) and NEC3 contracts are also TfL's contracts of choice, being those considered most likely to achieve a successful outcome".
Hear from Chris Dulake, Crossrail Chief Engineer and David Morrice, Delivery Contracts Director, on how NEC Contracts have been used on Crossrail.
ECC, PSC and FC
A full range of NEC3 contracts are being used. Programme partner Transcend a joint venture of Aecom, CH2M Hill and Nichols Group is engaged under a £100 million NEC3 Professional Service Contract (PSC), and project delivery partner Bechtel is similarly engaged under a PSC worth £400 million.
Design framework agreements totalling £300 million have been secured by twelve engineering consultancies, along with enabling works framework agreements with 17 contractors worth £350 million. All of these are based on the NEC3 Framework Contract (FC).
Three major tunnelling contracts worth £1.25 billion were awarded in 2010 under the NEC3 Engineering and Construction Contract option C (target contract with activity schedule). The largest of these for the eastern running tunnels, worth over £500 million, went to a joint venture of Dragados and John Sisk. A joint venture of Bam Nuttall, Ferrovial Agroman and Kier Construction won a combined contract for the western running tunnels and station tunnels, also worth £500 million. The third contract for the eastern station tunnels was awarded to a joint venture of Balfour Beatty, Vinci and Morgan Sindall.
Over 20 more major ECC contracts will be awarded in 2011 and 2012, including £1.5 billion for the six central stations.
Benefits of NEC3
- Supports the clients desired culture and way of working and sends a message of intent to the industry.
- Can be used for all project requirements to give consistency in approach.
- Provides robust contract management processes and achieves a fair and sensible allocation of risk.