If an estimate for a compensation event is wrong e.g. £10k but it actually cost £12k is it revisited based on the actual cost?
No, once ‘implemented’ (see clause 65.1 for the three reasons) then the compensation event is not revised if the forecast is wrong (clause 65.2).