I tend to find that on long term contracts the key people can change – how is this managed under the Term Service Contract?
The key people are defined in Contract Data part two. Clause 24.1 defines the protocol for replacing them. The replacements should have similar qualifications and experience as the person they have replaced. They also need to be accepted by the Service Manager.