If we have a compensation event and we also have a rate for this in the Price List do we use the Price List rate or assess this on Defined Cost?

Clause 63.1 defines that if you have a compensation event which only effects the quantities in the Price List then you would assess this by multiplying the changed quantities by the appropriate rates in the Price List