Could you advise if the use of batch orders can be applied under the NEC3 Supply Contract (SC) and if so, what costs are we as the purchaser liable to pay if not all batch orders are required.
For that reason it is not suitable for relatively straightforward call-off type supplies, where easily identifiable goods can be priced and called off as and when needed, with no need for any further goods information to be provided. Therefore we recommend that you should use the NEC3 Supply Short Contract (SSC) for this type of supply, as it is specifically designed for it.