NEC early warning notices: a unique risk management tool of mutual benefit

Over the years I have received regular  feedback from construction firms regarding the operation of NEC early warning notices. They normally comprise one or more of the following comments. 
  • ‘I always issue early warning notices, whatever the problem, to ensure I get a compensation event.’
  • ‘The other side issues early warning notices to establish it is my fault and I have to fix it immediately.’
  • ‘I am wary of issuing early warning notices because the other side uses them against me in the event of a dispute.’
  • ‘Everyone on the project ignores early warning notices.’
It is clear from my feedback that there are still some misconceptions about NEC early warning notices. 

Risk management tool

The first thing to note is that early warning notices have been a feature of NEC from the start – their inclusion separated NEC from the rest of the contractual pack. They were introduced as a risk management tool because it is common sense that dealing with risk – wherever it comes from – as soon as it becomes apparent is far cheaper than trying to manage the risk and/or its consequences much later on.

Clause 16 of most NEC contracts makes clear the circumstances in which either party would be expected to issue an early warning notice. An early warning notice must be issued as soon as a party becomes aware of ‘any matter’ which could affect the total of the prices, could delay completion or a key date, or impair the performance of the works in use. 
 
Also, the contractor may give an early warning notice relating to any matter which could increase its total cost. Early warning matters should be entered on the risk register.

Mutual benefit to parties

Early warning notices should not be issued for the purpose of allocating responsibility or liability. In fact a party attempting to do this could be failing to act in the NEC clause 10, ‘spirit of mutual trust and co-operation’. When dealing with matters which are the subject of an early warning notice, the emphasis should be on agreeing on the steps required to address the matter rather than on allocating blame.

Certainly ignoring early warning notices is a dangerous game. Apart from a possible breach of clause 10, any compensation event that may follow is likely to be costlier to the client than if the matter had been dealt with at the outset. But remember there is no direct link between early warning notices and compensation events – an early warning notice might not lead to a compensation event, and a compensation event might occur without an early warning notice.
 
Some of the confusion around early warning notices can be accounted for by people having grown up within an adversarial contracting culture. Such culture should be discarded when using NEC. 

The sooner we can appreciate that early warning notices are a tool of mutual benefit to both parties – and are not designed to advantage one side over the other – the better.
  NEC Users Group President
Recent Projects

Recent news

Avoid a battle of the forms by using a single set of terms and conditions

Avoid a battle of the forms by using a single set of terms and conditions

To avoid unnecessary disputes, NEC4 FC work orders should ideally be let under other NEC4 contracts and include the same contract data.

Read more
NEC used to deliver world-leading cancer research centre in Manchester, UK

NEC used to deliver world-leading cancer research centre in Manchester, UK

The Paterson Building in Manchester, UK is one of the world’s leading cancer research centres.

Read more
Upcoming NEC Training in Asia Pacific 2025

Upcoming NEC Training in Asia Pacific 2025

Explore our upcoming NEC training courses in Hong Kong, Singapore and Australia

Read more
View all news