Guidance on Using NEC for Ground Investigations

Guidance on Using NEC for Ground Investigations

NEC contracts have been designed to be used in most types of work relating to the built environment. Ground investigation contract works can be procured using NEC forms. This guidance gives advice on how to implement this and deal with the specific requirements of ground investigation contracts.

Ground investigation works generally consist of two parts:

  • The physical work of drilling, boring, excavation, sampling, in situ testing and monitoring
  • Surveying, analysis, laboratory testing and reporting of findings

Because of the nature of the physical work, one of the “works” contracts in the NEC family will normally be appropriate, either the Engineering and Construction Contract (ECC) or the Engineering and Construction Short Contract (ECSC). Whilst a Professional Service Contract (PSC) could be appropriate for desk studies, guidance and reporting, it is not suitable for site works.

For simple, straightforward ground investigations the ECSC could be suitable. For larger scale, more complex and higher risk projects the ECC would normally be used. Further details setting out the key differences between the ECC and the ECSC can be found here.

Find out more about how these contracts can be used for ground investigation projects by downloading the new practice note using the button below.

Download the Guidance Note
Recent Projects

Recent news

Avoid a battle of the forms by using a single set of terms and conditions

Avoid a battle of the forms by using a single set of terms and conditions

To avoid unnecessary disputes, NEC4 FC work orders should ideally be let under other NEC4 contracts and include the same contract data.

Read more
NEC used to deliver world-leading cancer research centre in Manchester, UK

NEC used to deliver world-leading cancer research centre in Manchester, UK

The Paterson Building in Manchester, UK is one of the world’s leading cancer research centres.

Read more
Upcoming NEC Training in Asia Pacific 2025

Upcoming NEC Training in Asia Pacific 2025

Explore our upcoming NEC training courses in Hong Kong, Singapore and Australia

Read more
View all news